SAGARMALA SCHEME IN KARNATAKA
SAGARMALA SCHEME IN KARNATAKA
Under Sagarmala Scheme, 8 projects worth Rs. 493 cr. have been sanctioned in the State of Karnataka. The details of projects sanctioned under Sagarmala scheme in the State of Karnataka are annexed [Annexure-I]. Coastal Berthing Scheme of the Ministry was merged with Sagarmala Scheme in September, 2016.
The project UNNATI was envisaged only for the Major Ports which are under the administrative control of the Ministry of Ports, Shipping and Waterways. The status of project UNNATI initiatives in New Mangalore Port Authority (NMPA) is annexed. [Annexure-II]. Infrastructure upgradation works carried out at NMPA is annexed [Annexure-III]
Annexure I
S N
Project Name
Implementing Agency
Cost
(INR Cr)
Funds Sanctioned
(INR Cr)
Status
1
Modernisation of the existing fishing harbour at Amadalli
Dept. of Fisheries
19
4.68
Completed
2
Third stage expansion including modernisation of the existing fishing harbour of Malpe
Dept. of Fisheries
50
7.94
Completed
3
Coastal Districts Skill Development Program – Phase I -Karnataka
Ministry of Rural Development (DDU-GKY)
1.53
0.76
Completed
4
Development of Fishing Harbour at Kulai
NMPA
197
98.5
Under Implementation
5
Construction of coastal cargo berth at Old Mangaluru Port
Karnataka Maritime Board
65
25.00
Under Implementation
6
Coastal Districts Skill Development Program – Phase II -Karnataka
Ministry of Rural Development (DDU-GKY)
2.18
2.18
Under Implementation
7
Development of HejmaadiKodi Fishing Harbour
Dept. of Fisheries
138.6
34.65
Under Implementation
8
Installation of Firefighting Equipment at Karwar
Karnataka Maritime Board
19.00
9.50
Under Implementation
Annexure-II
Initiatives covered under project UNNATI at NMPA
Initiative No.
Initiative
Status
1.1
Increase container cargo by attracting customers from Mysore and adjoining areas
Implemented
1.2
Improving service level of containers & providing equipment’s at berth no.8 for handling of containers
Implemented
2.1
Setup an LNG terminal at NMPT on a PPP basis
Dropped due to non-availability of sterile area in the port for the LNG Terminal.
3.1
Setup a mechanized fertilizer handling berth with silo storage and a bagging plant
Dropped due to negative market response
4.1
Reduce overtime costs by migrating to a three shift deployment for tugs, pilot launches and mooring boats
Implemented
Annexure-III
Details of infrastructural upgradation work carried out at NMPA
SL.
NO
PROJECT NAME
Awarded Project Cost(Rs.CR)
1
Providing pavement quality concrete to the existing truck parking terminal near K.K. Gate adjacent to toilet block and construction of canteen, dormitory, shops, clinic building And toilet block in Truck Parking Terminal
5.81
2
Strengthening & widening to 4 Lane of existing road from KK Gate To Baikampady Tank Bund Road with pavement quality concrete at NMPA
22.52
3
Construction of Berth No.17
177.37
4
Modification to the KK Gate Entrance and Exit gate Including essentials amenities(with 4 Lane)
5.29
5
Construction of Cruise Terminal Gate
1.83
6
Construction of 2 Nos of covered storage sheds in Wharf Area
17.03
7
Providing pavement quality concrete to additional truck Parking Terminal on North Side of existing truck parking area near KK Gate
4.12
8
Providing pavement quality concrete for development of platform South Side of Railway track Inside Wharf Area
3.72
9
Development of truck parking area by providing pre cast blocks near Tannirbhavi Road at NMPA
7.28
10
Providing M30 Grade concrete for remaining portion of Berth No.2 inside Wharf Area
1.07
11
Providing pavement quality concrete for development of MDL Yard inside Wharf Area
14.90
12
Construction of compound wall from jetty No 13 gate to Jetty No 12 Gate at oil jetty area
1.53
13
Construction of security watch tower near Northern Breakwater At NMPA
0.48
This information was given by the The Union Minister of Ports, Shipping & Waterways, Shri Sarbananda Sonowal in a written reply in Lok Sabha today.