MSME Ministry’s Cluster Development Programme Shows Strong Progress in Telangana
MSME Ministry’s Cluster Development Programme Shows Strong Progress in Telangana
Micro and Small Enterprises-Cluster Development Programme (MSE-CDP) of Ministry of Micro, Small and Medium Enterprises, Government of India establish Common Facility Centers (CFCs) and create/upgrade Infrastructure Facilities (ID Projects) providing financial support to enhance the productivity and competitiveness of Micro and Small Enterprises (MSEs) in the existing cluster. The detail of the Common Facility Centers (CFCs) approved in Telangana under MSE-CDP, is as under:
S. No.
Name of the CFC Projects
Districts
Sector
Project Cost
GoI Grant Approved
Status
(Ongoing/ completed)
(Rs. In lakh)
1
Gold Ornament Cluster
Karimnagar
Gem & Jewelry
580.00
446.00
Ongoing
2
Rice Mill Cluster
Jagitial
Agro-processing
998.00
798.40
Ongoing
And, the detail of the Infrastructure Development (ID) Projects approved in Telangana under MSE-CDP, is as under:
S. No.
Name of projects
District
Total Project Cost
Approved GoI grant
Status (Ongoing/ completed)
(Rupees in lakh)
1
New Industrial Estate at Gujularamaram
Ranga Reddy
347.00
139.00
Completed
2
New Industrial Estate at Automotive & Engineering Cluster Park, Toopran Mandal, Medak
Medak
940.82
752.65
Completed
3
New Industrial Estate at Madikonda Village, Warangal District
Warangal
1061.19
735.6
Completed
4
Upgradation of Industrial Park at Palvancha,
Bhadradri Kothagudem
1014.76
800.00
Ongoing
5
Flatted Factory Complex at Chandenvalle, Ranga Reddy
Ranga Reddy
1541.04
1180.88
Ongoing
6
Flatted Factory Complex at Jadcherla
Mahbubnagar
1515.64
1160.39
Ongoing
7
Flatted Factory Complex at Madikonda,
Warangal
1549.35
1161.95
Ongoing
8
Flatted Factory Complex at Tuniki Bollaram,
Siddipet
1467.79
1106.45
Ongoing
9
Flatted Factory Complex at Dandu Malkapur, Yadadri
Bhuvanagiri
1460.00
1137.57
Ongoing
10
Marketing Hub – (Women Entrepreneurs International Trade & Technology Centre) at Nandigama Village, Patancheru Mandal
Sanga Reddy
1150
680
Ongoing
11
New Industrial Park at Narmala, Rajanna Sircilla
Rajanna Sircilla
1043.47
758.3
Ongoing
12
New Industrial Estate (Kakatiya Mega Textile Park) at Warangal Rural
Warangal
1010.4
683.29
Ongoing
13
Up-gradation of Industrial Park at Gadwal, Jogulamba Gadwal
Jogulamba Gadwal
1000.63
800
Ongoing
14
Up-gradation of Industrial Park at Mancherial
Mancherial
702.26
561.81
Ongoing
15
Upgradation of Industrial Estate at Jadcherla
Mahbubnagar
733.6
586.88
Ongoing
16
Upgradation of Industrial Estate at Jeedimetla
Medchal-Malkanjgiri
1000
800
Ongoing
17
Up-gradation of Industrial Estate at Cherlapally Industrial Esate, Medchal District
Medchal
1030
600
Ongoing
18
New Industrial Estate at Industrial Estate at Armoor
Nizamabad
935.09
674.09
Ongoing
19
New Industrial Estate at Ravalkole (V), Malkajgiri
Malkajgiri
1036.57
710.80
Ongoing
20
New Industrial Estate at Buggapadu
Khammam
848.13
559.25
Ongoing
21
New Industrial Estate at Kallem
Jangaon
1070.88
678.88
Ongoing
22
New Industrial Estate at Autonagar, Kundanpally Village, Ramagundam Mandal
Peddapalli
990.75
656.62
Ongoing
23
New Industrial Estate at Sultanpur
Sanga reddy
940.05
637.70
Ongoing
24
Up-gradation of Industrial Park at Autonagar, Hyderabad
Ranga Reddy
1054.26
650.65
Ongoing
25
Up-gradation of Industrial Park at Bhongir
Yadadri Bhuvanagiri
714.17
484.13
Ongoing
26
Setting up of New Industrial Estate, Mandapally
Siddipet
1007.62
610.88
Ongoing
MSE-CDP is a demand driven Central Sector Scheme wherein, State Governments send proposals as per common needs of existing cluster in their States/UTs which commonly result in enhanced employment.
This information was given by the Minister of State for Micro, Small and Medium Enterprises Sushri Shobha Karandlaje in a written reply in Lok Sabha today.
****