COMMISSIONING OF VIZHINJAM INTERNATIONAL SEAPORT
COMMISSIONING OF VIZHINJAM INTERNATIONAL SEAPORT
As per the schedule furnished by the Concessionaire, the project is scheduled for commission by December, 2024.
The amount utilised each by the Central Government, State Government and other agencies in the project is tabulated below:-
Amount Utilised by Central Govt.
Amount Utilised by State Govt. of Kerala
(As on 30.06.2024)
Amount Utilised by Other Agencies (Concessionaire – M/s Adani Vizhinjam Port Pvt. Ltd.)
As on 31.03.2024)
Nil
Rs. 1,892.42 crore
Rs. 4,255 crore
As per target the rail connectivity is scheduled for completion upto March, 2028. The port approach road has been targeted for establishment by M/s Adani Vizhinjam Port Pvt. Ltd. (AVPPL) by December, 2024.
This information was given by the Union Minister of Ports, Shipping and Waterways Shri Sarbananda Sonowal in a written reply in Rajya Sabha today.