WORK AND ACHIEVEMENTS UNDER PM-JANMAN
WORK AND ACHIEVEMENTS UNDER PM-JANMAN
In Rajya Sabha, the Union Minister of State (MoS) for Tribal Affairs Shri Durgadas Uikey replying today to an un-starred question of Shri Neeraj Dangi informed that on 15th November 2023, Hon’ble Prime Minister launched Pradhan Mantri Janjati Adivasi Nyaya MahaAbhiyaN (PM JANMAN) for socio-economic development of 75 PVTG communities residing in 18 states and one UT. The mission aims to provide basic facilities to improve their socio-economic conditions such as safe housing, clean drinking water and improved access to education, health and nutrition, road and telecom connectivity, electrification of unelectrified households and sustainable livelihood opportunities in 3 years. These objectives are being met through 11 interventions implemented by 9-line Ministries. PM JANMAN has total budgetary outlay of ₹24,104 Cr (Central share: ₹15336 Cr and State share: ₹8768 Cr). Each Ministry under abhiyan is responsible for implementing the intervention assigned to it. The actual release of funds under the abhiyan is subject to specific guidelines of concerned interventions as per the approved norms and submission of proposals by concerned States / UTs / IAs as per prescribed guidelines / procedures. The details of progress under the abhiyan is given in Annexure-I.
Under the abhiyan, beneficiaries of VDVKs are being been imparted training on Entrepreneurship, Skill Development, and Value addition through NIESBUD, Ministry of Skill Development and Entrepreneurship. Further, in coordination with State Governments, IEC camps have been organized which were aimed at awareness generation and facilitating in preparation of basic documents like Aadhar Card, Caste certificate, Jan Dhan bank account which are required for availing benefits under different schemes including Ayushman Card, PM Awas, MNREGA etc.
Annexure I
The details of progress under the PM-JANMAN
Name of Ministry
Activity
as on date 30.6.2025
Sanctioned details
Physical Achievements
M/o Rural Development
Provision of pucca houses
462159 houses
136112 houses completed
Connecting roads
6506.3 km
637 km
M/o Jal Shakti
Piped Water Supply
18385 Villages
7406 Villages
M/o Health and Family Welfare
Mobile Medical Units
694 MMU
694 MMU
M/o Women and Child Development
Construction and running of Anganwadi Centres
2500 AWCs
2027 AWCs Operational
M/o Education
Construction and running of hostels
492 Hostels
99 Hostels work started
M/o Power
Energization of unelectrified HHs
143194 HHs
120227 HHs
M/o New and Renewable Energy
Households sanctioned under New Solar Power Scheme
9961 HHs
2363 HHs
M/o Communications
Installation of mobile towers
3894 habitations planned for Coverage
2516 Habitations covered
M/o Tribal Affairs
Multipurpose Centers
1000 MPCs
802 MPCs work started
Setting up of VDVKs
516 VDVKs
332 VDVKs Business Started
*As per information from concerned Ministries.